Stirton & Stinson Housing

18 Stirton St., Brantford, ON
1 Storey | 1,700 sq. ft.
Client: City of Brantford
Type: Affordable Housing
Modular Components: 5
Modular Units: 4
Factory Fabrication: 2 months
Site Installation: 3 months from permit to occupancy
Project Scope: Full modular design, fabrication, delivery, and installation
This CASE Homes project delivered four modular residences, including one fully accessible unit, under the Rapid Housing Initiative. Fabrication ran in parallel with permitting, allowing all homes to be set in three hours once approvals were issued. Roofing and cladding were completed within five days to quickly establish a weather-tight envelope.